21-11-2026 12:00:00 AM
New Delhi: In a significant ruling reinforcing tribal land rights and statutory safeguards under the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (RFCTLARR Act), the Supreme Court of India set aside land acquisition proceedings initiated by the Odisha government in Scheduled Areas of Sundargarh district for limestone mining linked to Dalmia Cement Bharat Limited.
The Bench of Justices Dipankar Datta and Satish Chandra Sharma held that prior consent of the Gram Sabha under Section 41(3) of the 2013 Act is mandatory for acquisitions in Scheduled Areas and cannot be treated as merely directory. The acquisition covered agricultural lands in villages including Kukuda, Bihabandha and Lanjiberna.
The State had proceeded despite Gram Sabha resolutions dated 26 January 2020 that expressly rejected the proposal. The Orissa High Court had earlier upheld the process, characterising the consent requirement as directory and finding substantial compliance. The Supreme Court rejected this interpretation as “wholly erroneous,” emphasising that Section 41(3) imposes a binding obligation precisely to protect communities in Fifth Schedule areas. Non-compliance vitiates the entire acquisition.
The Court further clarified that where land is acquired for a private company (Section 2(2)(b)), prior consent of at least 80% of affected families must be obtained during the Social Impact Assessment stage and before the government examines the proposal under Section 8. Subsequent or post-facto consent cannot cure the defect. The existence of a mining lease under the Mines and Minerals (Development and Regulation) Act does not exempt the acquirer from the 2013 Act’s procedural and participatory safeguards; mere payment of compensation for damage is not equivalent to acquisition of title.
Additional infirmities included the composition of the Expert Group, which compromised independence under Section 7. The Court allowed the appeal, quashed the acquisition notifications and consequential orders, and set aside the High Court judgment, while leaving the State free to initiate fresh proceedings strictly in accordance with the law and the principles laid down.
The decision strengthens the protective architecture of the 2013 Act for Scheduled Areas, underscoring that development projects involving private entities cannot override mandatory community consent mechanisms. It serves as a clear precedent that legislative safeguards for tribal and local self-governance cannot be diluted through administrative convenience or expansive readings of “directory” language. The judgment is of particular importance for mining and industrial projects in Fifth Schedule regions across India.