SAS I-Tower buyers in limbo

18-11-2026 12:00:00 AM

400 buyers suffer due to dispute between developer and land owners

* Telangana RERA, in its August 23, 2025 order, held the developer and landowners jointly responsible for completing the project. It directed future project receipts into a dedicated RERA account, subject to engineer, architect and chartered accountant certification, along with quarterly disclosures and monitored construction milestones.

metro india news  I hyderabad : Investing in commercial property with the hope of earning regular rental income is a popular choice among buyers. But for more than 400 investors in Hyderabad's Khajaguda, the promise of attractive returns has given way to uncertainty, with the controversial SAS I-Tower project caught in a prolonged dispute between its developer and landowners.

The 37-storey commercial project, located at Survey No. 19 in Khajaguda, was undertaken by SAS Infra, now known as SAS I Tower Private Limited. The development agreement was executed on August 16, 2018, covering a proposed development on a 10.32-acre land parcel. The project received RERA registration on June 12, 2019.

However, construction failed to meet the expected timelines. According to proceedings before Telangana RERA, work had reached approximately 75–85 per cent before slowing down and eventually stalling towards the end of 2024.

The dispute took a serious turn when the landowners submitted an internal construction estimate prepared by the project's then Head of Construction on December 26, 2024. It placed the remaining construction requirement at approximately Rs 817 crore. The landowners claimed that the total requirement could exceed Rs 1,000 crore after including financing costs, assured returns to investors and the common-area maintenance corpus.

The landowners also alleged that funds collected from buyers were diverted to other real estate ventures and questioned the project's financial viability. The developer rejected these allegations, blaming land-title complications and restrictions imposed by the landowners on sales and funding.

A separate controversy concerns a reported title dispute involving 3.24 acres. A police complaint alleged that an earlier gift deed relating to the land had not been properly disclosed. A criminal case was registered against the landowners in June 2025. Reports also stated that a proposed Rs 255-crore bank loan was held up over title-related concerns.

The developer, meanwhile, cited FIR No. 887/2023, arbitration proceedings and subsequent settlement agreements in its dispute with the landowners. Buyers have also raised concerns over contractual commitments, including compensation, interest and refunds in the event of delayed possession. With the developer publishing construction updates as recently as August 2026, the crucial questions remain: What is the actual completion status, who will meet the remaining costs, and when will buyers finally receive their promised commercial spaces?